09.06.26
The electrical ducting, lighting pole and ballstop pole bases are now complete.
The fencing and kerbing has commenced.
Great work being done and it’s full steam ahead for the next couple of weeks in preparation for the final layer of stone and carpet





29.05.26
Work continues at pace on the Astro Pitch.
The stone subase is now complete.
Electrical ducting, Lighting pole and Ballstop bases are currently going in.
The pitch railing and kerbing will commence in the next week or so.